Resolution Approving Change Order #2 for the Outfall Diffuser Project

Information

Department:City ManagerSponsors:
Category:Change Order

Attachments

  1. Printout

Body

WHEREAS, on April 5, 2016 the City of Asbury Park received three (3) bids for the project named “Ocean Outfall and Difuser Repair”; and

 

              WHEREAS, TNJ Marine Inc., has been awarded the contract to repairs the Outfall Diffuser; and

 

              WHEREAS, TNJ Marine Inc., was awarded the base bid and Alternate A-1 in the amount of $365,700; and

 

WHEREAS, the project requires Changer Order #2 in the amount not to exceed twenty six thousand, seven hundred seventy five dollars and zero cents ($26,775.00); and

 

WHEREAS, this change order reflects the costs activities as attached in the letter received March 15, 2017 by the Project Engineer, T&M Associates, outlining the scope and cost of services; and

 

WHEREAS, the Project Engineer recommended that Change Order No. 2 be authorized to complete the Project; and

 

WHEREAS, the execution of Change Order No. 2 will not substantially change the quality or character of the items or work to be provided, inasmuch as such would not  have been a determining factor in the original bidding; and

 

WHEREAS, the execution of Change Order No. 2 will not cause the originally awarded contract price to be exceeded by more than 20% as the percent change in the contract is 13.7%; and

 

WHEREAS, the Chief Financial Officer has provided to the Governing Body a certificate in writing pursuant to N.J.A.C. 5:34-2 that funds are available to pay for the subject matter of this Resolution; and

 

WHEREAS, said certification has designated specifically the line item appropriation(s) of the official budget to which the contract will be officially charged.

 

NOW, THEREFORE, BE IT RESOLVED by the Mayor and City Council of Asbury park, County of Mayor and State of New Jersey that the this Change Order shall not exceed $26,775.00 And

 

BE IT FURTHER RESOLVED that the City Manager and Project Engineer is hereby authorized to execute Change Order No. 2 on behalf of the Governing Body; and

 

BE IT FURTHER RESOLVED that the contract between the parties referred to above shall be amended to reflect the changes approved herein; and

 

BE IT FURTHER RESOLVED that a certification of availability of funds shall be attached to the original copy of this resolution and kept in the files of the City Clerk.

 

NOW, THEREFORE, BE IT FURTHER RESOLVED that a copy of this Resolution be provided to the CFO, Project Engineer, Superintendent of Public Works, and City Manager.

 

 

Meeting History

Mar 22, 2017 7:00 PM  Municipal Council Regular Meeting
RESULT:ADOPTED [UNANIMOUS]
MOVER:Eileen Chapman, Councilmember
SECONDER:Amy Quinn, Deputy Mayor
AYES:Eileen Chapman, Yvonne Clayton, Jesse Kendle, Amy Quinn, John Moor